Busway Traffic Bulletin: Saturday 21 to Friday 27 April

Infonews Editor

Friday 20 April 2007, 3:44PM

By Infonews Editor

190 views

AUCKLAND

Transit New Zealand advises motorists of next week's proposed closures for work on State Highway 1 for Northern Busway construction (weather permitting).

ESMONDE RD
Sunday 22 April
Northbound off-ramp from SH1 to Esmonde Rd - CLOSED - overnight from 9pm until 5am for paving works.

Motorists are advised to follow the diversion via Northcote Rd off-ramp northbound
If unforeseen circumstances prevent work at the above time, the closure will be on
Monday 23 or Thursday 26 April

Sunday 22 April
Akoranga Dr eastbound link to Esmonde Rd - CLOSED - overnight from 9pm until 5am for paving works.

Motorists are advised to follow the diversion via Northcote Rd
If unforeseen circumstances prevent work at the above time, the closure will be on
Monday 23 or Thursday 26 April

Sunday 22 April
Esmonde Rd between Barrys Point Rd & Lake Rd - CLOSED - overnight from 9pm until 5am for paving works.

Motorists are advised to follow the diversion via Lake Rd & Anzac Ave
If unforeseen circumstances prevent work at the above time, the closure will be on
Monday 23 or Thursday 26 April

Monday 23 & Thursday 26 April
Southbound on-ramp from Esmonde Rd to SH1 - CLOSED - overnight from 9pm until 5am for paving works.
Motorists are advised to follow the diversion via Northcote Rd or Onewa Rd on-ramp southbound.

If unforeseen circumstances prevent work at the above time, the closure will be on
Sunday 22 April

Thursday 26 April (closure will only be required if wet weather postpones previous weeks work)
All SH1 motorway lanes southbound between Esmonde Rd & Onewa Rd - CLOSED - overnight from 10pm until 5am for placement of services chamber.

Motorists are advised to follow the diversion via Onewa Rd on-ramp southbound
NORTHCOTE RD
Sunday 22 April
Southbound on-ramp from Northcote Rd to SH1 - CLOSED - overnight from 9pm until 5am the following morning for services chamber construction.

Motorists are advised to follow the diversion via Onewa Rd & Esmonde Rd on-ramp southbound
If unforeseen circumstances prevent work at the above time, the closure will be on Monday 23 & Thursday 26 April
Sunday 22 & Monday 23 April (closure will only be required if wet weather postpones previous weeks work)
Northbound off-ramp from SH1 to Northcote Rd - CLOSED - overnight from 9pm until 5am the following morning for paving works.

Motorists are advised to follow the diversion via Tristram Ave off-ramp northbound
CONSTELLATION DR
Monday 23 April
Southbound on-ramp from Constellation Dr to SH1 - CLOSED - overnight from 10pm until 5am the following morning for construction of permanent barrier.

Motorists are advised to follow the diversion via Tristram Ave on-ramp southbound
Monday 23 April
All SH1 motorway lanes southbound between Constellation Dr & Tristram Ave - CLOSED - overnight from 10pm until 5am the following morning for construction of permanent barrier.

Motorists are advised to follow the diversion via Tristram Ave on-ramp southbound
If any of the contingency dates are required then all work planned for adjacent junctions will be reviewed to ensure that no two consecutive over bridges or interchanges are closed at the same time.

Road users are requested to use the sign posted detours whilst the closures are in operation.

Transit New Zealand apologises for any inconvenience caused.

Transit New Zealand
Northern Busway Senior Project Manager
Mark Johnson
(09) 486 0054

Visit www.busway.co.nz or www.transit.govt.nz for more information on the project.